Author: Bjørn Lovén
 |
Here we see the final preparations before closing down
boat traffic in and out of Zea while conducting survey dives
in the harbour mouth. |
| |
 |
Zea Harbour, area designation |
| |
 |
Sigrid Eliassen and her assistant Matthew McCallum at
work |
| |
 |
Artistic reconstruction of this part of the harbour |
| |
 |
Artistic reconstruction of this part of the harbour |
Work at Zea began early in 2005, as staff of the Zea Harbour Project
were invited to assist in rescue excavations directed by Dr. Kourkoumelis
of the Ephorate of Underwater Antiquities. The work ran from February
to August 2005. The construction of a number of floating jetties
anchored with massive concrete blocks is planned as part of the
general modernisation of the Marina.
An extensive underwater survey including rescue excavations was
conducted to ensure that submerged antiquities would not be damaged.
The results were many - the most important of which was that remains
of the foundations of the fortified harbour mouth, that made it
possible to close the harbour were located in the harbour basin.
The Hellenic Coast Guard worked in close co-operation with the team
It was during these dives that parts of the foundations of the
fortified harbour mouth were discovered. The intensive investigations
ensured that the construction plans were adjusted to provide maximum
protection to the antiquities at Zea.
In 2005 the work of the Zea Harbour Project focused mainly on the
harbour fortifications in Area 3 and Area 4. We also conducted survey
and excavations of shipsheds in Area 2 and Area 3.
AREA 4
Sigrid Eliassen and her assistant Matthew McCallum at work
In Area 4 the partly submerged quarry integrated into the harbour
fortifications was surveyed. The fact that the quarry was integrated
into the Classical fortification wall demonstrates that it was quarried
before or during the construction of the wall, thus the quarry cuttings
on land can be roughly dated to the Classical Period.
Project architect Sigrid Eliassen and her assistant Matthew McCallum
produced detailed 3D plans of 55 m of the fortification wall which
is still preserved to a height of up to 2.5 m, and 73 m of quarry.
All this was were done in five weeks, and this shows the potential
of modern precision surveying.
AREA 3
Excavations began where the shipshed complex ends and the harbour
fortifications begin. Four Phase II shipsheds have been identified
while surveying in the northern part of Area 3. The eastern part
of these buildings was later quarried after the shipsheds went out
of use. Another shipshed and a quarry were found further to the
north.
AREA 2
In Area 2 excavations were carried out on five structures, three
of which had been found during the 2001 survey. The southern side
of Structure 4 has the same orientation as the Phase II shipsheds
to the south, whereas the western side is oriented to the Phase
I shipsheds (these building phases are specific to this area, and
should not be compared to the Area 2 shipsheds).
Structure 4 is probably related to the shipshed complex, and may
connect the Phase I shipsheds still in use to the north and the
more recent Phase II shipsheds to the south. Structure 5 is tentatively
identified as part of a Phase I ramp, and the structure could date
to the 5th cent. BC.
The most important discovery in this area was areas of stratified
layers, a rare phenomenon in the surf zone at Zea, and when Mette
Schaldemose has completed her studies of the excavated material
we will know more about the chronology of Structures 4 and 5.
No remains of the towers at the end of the fortified quays are
preserved at Zea. To obtain more information on the harbour fortification
the northern limen kleistos tower in Mikrolimano (ancient Mounychia)
was surveyed both on land and in the sea.
Most of the tower is destroyed but a substantial part of the north-western
side is still preserved and the remaining curve of the outer face
shows that the tower originally had a diameter of 12-13 m. The total
preserved height of the tower is 3.92 m, and if the foundations
are included it stands an amazing 9.24 m above the seabed.
With the permission of the Ephorate of Underwater Antiquities a
preliminary two day survey was carried out under water in other
parts of the Mounychia harbour in order to investigate if antiquities
are preserved in these areas. Possible remains of shipsheds were
found along the western side of the northern quay and in the northern
part of the harbour.
In the area opposite to the preserved limen kleistos tower a substantial
structure was found that in all probability belong to the southern
fortified quay. Further to the south were also located extensive
remains of the ancient harbour fortification. This two day survey
showed that extensive remains of the ancient naval installations
and harbour fortifications in Mounychia are still preserved in the
sea.
Finally we wish to report on a new research project. In February
2005 the CHIMERA project (Cultural Heritage Interactive Media Environment
for Reality Augmentation) was initiated as a joint venture between
Architecture and Design, Aalborg University, Denmark, and the Zea
Harbour Project.
The aim of the project is to create scientific three-dimensional
reconstructions visualising the naval installations of the Piraeus,
so real that you can smell the sea and hear lapping of the waves
against the lower ends of the slipways. The pilot product can down-loaded
from this link. (Right
click on the link and choose ‘save target as’)
|